December Haul-out - Preparation
Preparations, purchasing, measurements and decisions ahead of Greenroom's December 2026 hardstand.
Greenroom comes out at South of Perth Yacht Club on Friday 11 December 2026 at 11:00 am, and must leave the hardstand on Wednesday 23 December. This is the preparation checklist; the actual hardstand work plan tracks the jobs, daily decisions and progress once the boat is out.
Boat: 1976 Space Sailer 22, Greenroom
Status: Preparing
Preparation day: Friday 13 November 2026
Likely paint brand: Jotun, to be confirmed on Friday
Approach: Strip/sand back aged coatings as necessary, repair and repaint with rollers. Structural integrity and safe immersion take priority over finish.
Fixed departure: 23 December cannot slip. Confirm product cure and immersion windows before stripping large areas. Work left incomplete may need a second lift in early January, but the boat must not be launched with open holes, unsafe laminate repairs or unsuitable/exposed underwater surfaces.
Scope confirmed #
- Four old hull openings to close: one 25 mm sink outlet (not replaced), two 25 mm cockpit drains, and one 10 mm anchor-well drain. All have good access from both sides for grinding and fibreglassing.
- Three new hull outlets: two 25 mm TruDesign cockpit drains through the hull sides, and one 25 mm TruDesign anchor-well drain, positioned well above the waterline.
- The old cockpit drains exit underwater and have corroded bronze fittings. New drains are intended to have short, continuously falling hose runs through the aft locker, which is isolated from the cabin.
- No seacocks planned because the intended new outlets are above the applicable heeled waterline. Verify the actual marked positions and exact fitting installation instructions before drilling; do not rely solely on the cockpit floor's approximate 300 mm height above the upright waterline.
- Two 25 mm cockpit drains are understood to comply with the boat's class and intended use; retain the applicable rule/reference in project notes and check actual clear internal bore, hose configuration and drainage in use.
- Underwater antifoul is over ten years old and substantially worn away. Topsides paint is approximately 50 years old. Both are to be sanded/prepared for a new coating system. Avoid grinding away sound gelcoat or intact protective laminate unnecessarily.
- Keel has reported pitting; final substrate and treatment to be confirmed on inspection. Any osmosis work is limited by realistic drying and the fixed launch date.
Friday 13 November - dedicated preparation day #
1. Paint supplier - main objective #
2. On the boat - measurements and photos #
3. SoPYC - yard arrangements #
4. Tools, repairs and fittings - stocktake #
5. Friday wrap-up - decisions to record #
Decisions and open questions #
| Question | Current understanding | Resolution |
|---|---|---|
| Coatings | Likely Jotun; full systems not chosen | TBD Friday |
| Topsides colour | G32 Opaline | Confirm tint and product |
| Antifoul colour | Charcoal / close to B64 | Confirm availability |
| Existing topsides paint | Approximately 50 years old; sanding back planned | Confirm substrate and compatibility |
| Existing antifoul | Over 10 years old, worn away | Determine extent of removal and safe prep |
| Keel | Pitting reported | Confirm metal, preparation and primer |
| Four old holes | 25 mm sink; 2 x 25 mm cockpit; 10 mm anchor well | Confirm actual cut-out/laminate dimensions |
| Three new outlets | 25 mm TruDesign, two cockpit and one anchor well | Confirm model, exact position, fittings and hose run |
| Cockpit drainage | 2 x 25 mm meets class/use requirements | Record governing rule and check clear bore/functional flow |
| Heeled waterline | Outlets planned above it, no valves | Verify marked locations and installation specification |
| Osmosis | Unknown | Inspect after wash; defer widespread treatment |
| Time | Half-days Tue 15, Wed 16, Thu 17 Dec | Plan cure-friendly jobs for these days |
| Yard | 11 Dec lift, 23 Dec fixed departure | Confirm access hours and written booking |
Product and purchasing tracker #
| Bought? | Item | Product / specification | Quantity | Cost |
|---|---|---|---|---|
| Laminating epoxy and hardener | TBD | TBD | - | |
| Fibreglass cloth / reinforcement for four repairs | TBD | TBD | - | |
| Structural and fairing fillers | TBD | TBD | - | |
| Underwater epoxy primer / barrier | Likely Jotun | TBD | - | |
| Keel treatment / primer | TBD | TBD | - | |
| Antifoul, charcoal | Likely Jotun | TBD | - | |
| Topsides primer / undercoat | Likely Jotun | TBD | - | |
| Topsides finish, G32 Opaline | Likely Jotun | TBD | - | |
| TruDesign 25 mm outlets | Exact model TBD | 3 | - | |
| Drain hose, clamps, sealant | TBD | TBD | - | |
| Abrasives, rollers, consumables, PPE | TBD | TBD | - | |
| Hardstand first day deposit | Paid, confirmation pending | 1 | $413.03 | |
| Remaining yard charges | Confirm with SoPYC | TBD | - |
Expected total: TBD
Spent: $413.03 reported, plus new purchases as recorded.
Preparation log #
- 10 November: Tentative SoPYC booking for 11-23 December. Deposit paid and insurance emailed; still awaiting written confirmation and booking form status.
- 11 November: Scope corrected to four old underwater penetrations and three new 25 mm drains. Paint likely Jotun. Middle Tuesday/Wednesday/Thursday are half-days. Split plan into preparation and work pages.
- 13 November - dedicated preparation day:
Shop visit / products:
Measurements / photos:
Yard answers:
Purchases / costs:
Open questions / next steps:
Once preparation decisions are settled, keep this page as the purchasing and specification record, and track daily progress on the hardstand work plan.