December Haul-out - Preparation

Preparations, purchasing, measurements and decisions ahead of Greenroom's December 2026 hardstand.

Greenroom comes out at South of Perth Yacht Club on Friday 11 December 2026 at 11:00 am, and must leave the hardstand on Wednesday 23 December. This is the preparation checklist; the actual hardstand work plan tracks the jobs, daily decisions and progress once the boat is out.

Boat: 1976 Space Sailer 22, Greenroom
Status: Preparing
Preparation day: Friday 13 November 2026
Likely paint brand: Jotun, to be confirmed on Friday
Approach: Strip/sand back aged coatings as necessary, repair and repaint with rollers. Structural integrity and safe immersion take priority over finish.

Fixed departure: 23 December cannot slip. Confirm product cure and immersion windows before stripping large areas. Work left incomplete may need a second lift in early January, but the boat must not be launched with open holes, unsafe laminate repairs or unsuitable/exposed underwater surfaces.

Scope confirmed

Friday 13 November - dedicated preparation day

1. Paint supplier - main objective

2. On the boat - measurements and photos

3. SoPYC - yard arrangements

4. Tools, repairs and fittings - stocktake

5. Friday wrap-up - decisions to record

Decisions and open questions

Question Current understanding Resolution
Coatings Likely Jotun; full systems not chosen TBD Friday
Topsides colour G32 Opaline Confirm tint and product
Antifoul colour Charcoal / close to B64 Confirm availability
Existing topsides paint Approximately 50 years old; sanding back planned Confirm substrate and compatibility
Existing antifoul Over 10 years old, worn away Determine extent of removal and safe prep
Keel Pitting reported Confirm metal, preparation and primer
Four old holes 25 mm sink; 2 x 25 mm cockpit; 10 mm anchor well Confirm actual cut-out/laminate dimensions
Three new outlets 25 mm TruDesign, two cockpit and one anchor well Confirm model, exact position, fittings and hose run
Cockpit drainage 2 x 25 mm meets class/use requirements Record governing rule and check clear bore/functional flow
Heeled waterline Outlets planned above it, no valves Verify marked locations and installation specification
Osmosis Unknown Inspect after wash; defer widespread treatment
Time Half-days Tue 15, Wed 16, Thu 17 Dec Plan cure-friendly jobs for these days
Yard 11 Dec lift, 23 Dec fixed departure Confirm access hours and written booking

Product and purchasing tracker

Bought? Item Product / specification Quantity Cost
Laminating epoxy and hardener TBD TBD -
Fibreglass cloth / reinforcement for four repairs TBD TBD -
Structural and fairing fillers TBD TBD -
Underwater epoxy primer / barrier Likely Jotun TBD -
Keel treatment / primer TBD TBD -
Antifoul, charcoal Likely Jotun TBD -
Topsides primer / undercoat Likely Jotun TBD -
Topsides finish, G32 Opaline Likely Jotun TBD -
TruDesign 25 mm outlets Exact model TBD 3 -
Drain hose, clamps, sealant TBD TBD -
Abrasives, rollers, consumables, PPE TBD TBD -
Hardstand first day deposit Paid, confirmation pending 1 $413.03
Remaining yard charges Confirm with SoPYC TBD -

Expected total: TBD
Spent: $413.03 reported, plus new purchases as recorded.

Preparation log


Once preparation decisions are settled, keep this page as the purchasing and specification record, and track daily progress on the hardstand work plan.