December Haul-out - Work Plan

Daily hardstand schedule, four through-hull repairs, three new drains, hull and keel coatings, decision gates and relaunch checklist.

Greenroom is coming out at South of Perth Yacht Club Friday 11 December 2026 at 11:00 am and must be off the hardstand Wednesday 23 December. This is the daily work and progress tracker. The preparation page holds Friday's jobs, products, measurements, yard arrangements and purchasing.

Boat: 1976 Space Sailer 22, Greenroom
Status: Not started
Fixed launch / departure: Wednesday 23 December 2026
Limited availability: Tuesday 15, Wednesday 16 and Thursday 17 December are HALF-DAYS only. Other days depend on yard access hours.
Coatings: Likely Jotun, awaiting Friday 13 November product selection and technical sheets. All roller-applied.

Deadline rule: 23 December is a hard stop. Finish sound laminate repairs and safe, protected underwater surfaces before attempting cosmetic perfection. A January haul-out is an option for deferred paint and fairing, not for launching with open holes, uncured repairs or bare exposed underwater laminate. If the boat cannot be made seaworthy in time, organise a yard-approved alternative departure rather than force an unsafe launch.

Work scope and order

Priority 1 - make the hull safe

Priority 2 - durable protection

Priority 3 - appearance

Decision gates - preventing half-finished work

Date Go / no-go decision If behind
Before 11 Dec Exact paint system, coverage, recoat and immersion schedule known. New drains and four-hole layups planned. Don't buy/use incompatible paint or drill without a confirmed outlet plan.
Fri 11 Dec, after wash Identify osmosis, structural surprises and keel condition; decide how much coating can safely be removed. Defer extensive osmosis stripping, major keel work and unnecessary bare-laminate exposure.
Sun 13 Dec, evening Scope freeze for new invasive work. Four old openings should be prepared/repairs underway; three new drain locations confirmed. Stop opening extra blisters and stripping new areas; concentrate on repairs already begun.
Mon 14 Dec, evening All essential hole drilling and structural layup should be completed or have a fully achievable cure plan. Cancel cosmetic tasks; use the three half-days for cure, small finishing work, fitting and inspection.
Thu 17 Dec, evening Structural holes closed, drain penetrations sealed, drain installation on track. Enough coating time remains for 23 Dec immersion. Freeze further surface removal and fairing. Use Fri-Mon for necessary protection.
Fri 18 Dec, evening Decide full coating programme or minimum safe protection after checking actual temperatures and technical sheets. Defer topsides and nonessential antifoul; apply only a manufacturer-approved, fully cured underwater protective system.
Sun 20 Dec, evening No new optional sanding through coatings, drilling or blister excavation; only coats that can meet the launch window. Protect existing work and finish required immersion-safe coatings.
Tue 22 Dec Formal launch readiness: repairs sound/cured, drains tested, underwater surfaces protected, access/pad patches handled. Contact SoPYC and use a pre-arranged off-hardstand contingency if launch unsafe.
Wed 23 Dec Depart hardstand on time; relaunch only when seaworthy. Alternative move/transport, not a rushed unsafe launch.

Start-work test: Before each new patch, ask if I open this now, can I fully repair, seal, cure and test it by 22 December? If no, photograph it, leave the existing sound surface intact and record it for January unless it is a safety-critical defect.

Daily hardstand schedule

The first four days do the heavy structural work. The three half-days are reserved for curing, controlled fairing, fitting work and discrete painting tasks rather than relying on full-day labour. Later painting dates are provisional until the actual Jotun (or alternative) system is documented.

Date Availability Main work End-of-day checkpoint
Fri 11 Dec After 11:00 lift Arrive before 10:45; lift, pressure wash, photograph and inspect. Mark all four old holes, three new positions, osmosis and keel defects. Set up containment. Gate 1: decide realistic repair/stripping scope.
Sat 12 Dec Full day, subject to yard Remove sink, 2 cockpit and anchor-well fittings; prepare/taper four old holes. Initial antifoul sanding/stripping and inspect old laminate. Holes measured and prepared; all structural surprises identified.
Sun 13 Dec Full day, subject to yard Laminate four hole repairs. Dry-fit positions/routing for new drains; cut new holes only after design check. Start only local osmosis repairs that can dry and cure. Gate 2: no new invasive cosmetic scope after today.
Mon 14 Dec Full day Complete structural laminating and new penetrations/epoxy edge sealing. Continue controlled hull sanding and keel preparation; prime bare keel metal promptly where specified. Gate 3: leave no unplanned structural drilling for the half-days.
Tue 15 Dec Half day Inspect cured layups, blush wash/sand as specified; finish limited repairs/fairing. Dry-fit hose runs and fittings; install only where sealing epoxy ready. Four old holes watertight in progress; record cure/inspection.
Wed 16 Dec Half day Finish fittings/hoses and drainage testing as possible; precise sanding/fairing and mask. Prepare coating areas without new invasive work. No open structural work; coat readiness assessed.
Thu 17 Dec Half day Targeted primer or sealing coats that fit a short session and the exact overcoat timetable; finish any essential drain tests. Gate 4: coating plan definitely compatible with 23 Dec.
Fri 18 Dec Full day Complete hull/keel primer system as specified, or minimum safe immersion-ready protection. Start topsides coating only if underwater schedule secure. Gate 5: full-coat versus January fallback decision.
Sat 19 Dec Full day Finish permitted primer/topsides coats; start antifoul as dictated by technical sheets, preserving wet/paint-clean work areas. Recoat windows, temperatures and coat counts logged.
Sun 20 Dec Full day Underwater coats and antifoul as specified. No new optional material removal. Gate 6: no coating started that cannot cure for launch.
Mon 21 Dec Full day Finish remaining scheduled antifoul, high-wear areas and topsides details only if datasheets allow. Organise yard-assisted pad moves. All critical underwater protection complete.
Tue 22 Dec Full day Finish accessible pad spots with allowable cure; inspect and test drainage, repairs, hull/keel protection; photographs, tidy and final booking checks. Gate 7: launch-ready, or activate off-hardstand contingency.
Wed 23 Dec Relaunch / departure Check cure records and fitting integrity; launch at booked time, inspect leaks/backflow and trim immediately afloat. Record completion and January follow-up.

Coating timing note: Do not assume primer, topsides and antifoul can be arranged in the order shown without the supplier's TDS. Primer-to-antifoul windows, number of coats, air/substrate temperature and the cradle-pad access sequence may require reordering. For each product, calculate its latest allowable application time from the 23 December immersion and handling requirements.

Work instructions and quality checks

1. Lift, wash and inspect

2. Close four old through-hulls

3. Fit three new 25 mm drains

4. Prepare and roughly fair hull and keel

5. Apply coatings

6. Final launch checks

Coating application log

Fill this in after the final product selection. Do not use guessed times.

Area / coat Product / colour Applied date/time Temp / conditions Next coat or immersion deadline Notes
Underwater hull 1 TBD
Underwater hull 2+ TBD
Keel primer TBD
Topsides undercoat TBD
Topsides finish TBD
Antifoul 1 TBD
Antifoul 2+ TBD
Cradle-pad patches TBD

Findings and decisions register

Date Finding / problem Decision Action / owner

January contingency and deferred work

The deadline means some work may be consciously deferred. Do not compromise safe repairs merely to finish the paint.

Deferred work Reason / condition left in Next action Status

Daily log

Friday 11 December - lift, wash, inspection

Hours / weather:
Completed:
Findings / photos:
Scope decision:
Tomorrow:

Saturday 12 December - four old fittings

Hours / weather:
Completed:
Laminate / hole measurements:
Issues:
Tomorrow:

Sunday 13 December - repairs and scope freeze

Hours / weather:
Completed:
Repair layup / cure:
Scope freeze decision:
Tomorrow:

Monday 14 December - finish structural work

Hours / weather:
Completed:
Holes / new outlets status:
Half-day plan for 15-17 Dec:

Tuesday 15 December - HALF DAY

Hours available:
Completed:
Cure / checks:
Tomorrow:

Wednesday 16 December - HALF DAY

Hours available:
Completed:
Drain tests / fairing:
Tomorrow:

Thursday 17 December - HALF DAY

Hours available:
Completed:
Coating times / conditions:
Coating go/no-go:

Friday 18 December - coating scope decision

Hours / weather:
Completed:
Coatings / times:
Full finish or January fallback:

Saturday 19 December

Hours / weather:
Completed:
Coatings / times:
Tomorrow:

Sunday 20 December - no new optional surface work

Hours / weather:
Completed:
Coatings / times:
Latest safe launch cure:

Monday 21 December

Hours / weather:
Completed:
Coatings / times:
Remaining essential jobs:

Tuesday 22 December - launch readiness

Hours / weather:
Completed:
Drain / laminate / coating checks:
Launch-ready decision:
Items deferred:

Wednesday 23 December - fixed departure

Launch time:
Pre-launch inspection:
Leak / drain checks afloat:
Final condition:
January list:


The working plan is deliberately conservative: commit to structural repairs early; use the middle half-days for curing and finish-up; and let the product technical sheets, not optimism, control the final paint schedule.